Skip to content

Children’s Hospital and Clinics of Minnesota, MRI and CVICU

Replacement of a 1.5T magnet MRI with a 3T magnet MRI. Also included renovations of the surrounding areas, including ultrasound, EKG, carseat evaluation, apnea classroom, lounge, storage and workstations. Cost $2.5M Schedule: 6 months completed late 2017. CVICU was a renovation of finish upgrades to CVICU entry, corridor and a few office areas. Along with updated soiled utility, storage tank space and Pyxis alcove updates.

Project Details

Location
Minneapolis, MN
Status
Completed 2018
Delivery Method
CMAR
Architect
HDR, Inc.

Explore Our Portfolio